Construction Work Update October 2022
State of progress at the end of October 2022:
- the reinforced concrete work of the parking hall is ongoing; the foundations are complete and the wall of the parking hall is 80% complete;
- construction of the concrete part of the parking hall ceiling has been completed, and the reinforcement of the rest of the ceiling is currently underway (the completion of the entire parking hall ceiling is scheduled to be completed by the end of November 2022);
- the access route to the construction site and the rainwater drainage installation have been completed;
- the work is being carried out according to schedule, with more than 10% of the total construction work has now been completed.
Initial preparations, geological surveying, groundworks, and some construction and installation works are all due to be completed by the end of 2022.